Bently Nevada System 1: What to confirm before an upgrade

Oct 17, 2026

A practical guide to defining software work and preparing the right spare-parts enquiry for a planned shutdown.

Quick answer

Confirm the installed release, licence position and recovery plan before booking the upgrade. If the same shutdown needs hardware, identify each complete part number and revision separately. This gives engineering a defined change scope and purchasing a usable parts list.

Submit your parts list
Technician at a machinery-monitoring cabinet.

Start with the decision you actually need to make

A System 1 screen may still look normal when its release needs a support review. Treat the support date as a planning checkpoint alongside the condition of the server, database and operating system. Today's screen alone cannot tell you whether an upgrade can wait.

Your questionIs the installed release still supported?
Check firstExact System 1 release and applicable support documentation
Who should confirm it?Your software support provider
Your questionDoes the subscription need attention?
Check firstLicence entitlement, renewal date and applicable grace period
Who should confirm it?Your licensing contact
Your questionWill the shutdown also require spare parts?
Check firstFull part number, suffix, revision and rack application
Who should confirm it?Site engineering, followed by the parts supplier
Your questionIs infrastructure replacement approaching?
Check firstServer, operating-system and database versions; planned replacement dates
Who should confirm it?OT/IT and the responsible system engineer

Keep these as separate lines in the project scope. A hardware quotation should make clear which items are included; arrange software licensing and migration work with the relevant provider.

 

What the published release notes establish

Bently Nevada's November 2025 v25.2 release notes list the following support dates. Use this dated matrix with the documentation for your installation; it is not presented as the latest schedule.

System 1 release Published end of support
24.1 May 2026
24.2 November 2026
25.1 May 2027
25.2 November 2027

The notes distinguish two events: unsupported releases retain assistance for common FAQ-type questions without engineering escalation; a subscription past its grace period stops data and alarm-event collection until renewal.

Planning implication: check support, licence renewal and infrastructure retirement separately. Booking an upgrade does not resolve an earlier renewal deadline.

Choose a release around the plant's next constraints

Each upgrade consumes engineering time and introduces a change to validate. Waiting for a server failure can combine hardware recovery, compatibility work and historical-data access into one urgent job. Set the timing against the next planned site change and the required operating period.

Use the next site change as a decision point

  • Server replacement: review the software and database plan before selecting the replacement environment.
  • Rack retrofit: coordinate the intended software capability and hardware scope, with compatibility checked for the actual configuration.
  • Production campaign: consider completing the change beforehand, with time for validation and recovery.

Map the whole installation

For a multi-server installation, record which servers acquire data, replicate it and provide client access. Ask the upgrade provider to confirm the intended version relationships and licence requirements. A successful installation on one server does not demonstrate that the complete data path works.

Build a useful shutdown handover

Use this checklist to gather information. It is a planning aid; the migration method still needs approval for the actual installation.

Prove recovery before the maintenance window

For the documented move to System 1 25.1 or later, PostgreSQL 14 databases must move to PostgreSQL 17. Reverting the installation requires the specified VSS/Acronis backup, rather than simply uninstalling the upgrade.

A backup file alone does not show that the required environment can read it or that it contains the latest configuration and required history. Ask for a recovery rehearsal that demonstrates usable information, with a clear decision point for restoring service.

Allow for the database transition, validation and recovery decision in the maintenance window. Include database size, storage performance, backup location and connected or replicated servers in the estimate. The installer running quickly does not establish the duration of the complete change.

Put the starting point and acceptance checks in writing

  1. Record the starting point. Installed application release, database version, server operating system and acquisition/replication arrangement.
  2. Define the intended change. Target release, server changes, connected equipment and any separate rack work.
  3. Agree recovery and acceptance. Name the responsible person, backup location, recovery decision point and checks for new data, alarms and required history.
  4. Separate the purchasing list. Put each hardware requirement on its own line with the evidence needed to identify it.

Before approving the quotation, ask: who performs each task, what is excluded, and what evidence will show the work is complete?

 

An official case shows why the upgrade objective matters

Bently Nevada describes a natural-gas operator that moved selected critical assets to System 1 20.1 in mid-2020 and added Decision Support Analytics. The analytics identified two wiring-related alarm conditions; the operator's asset team checked them in System 1. The reported result was a corrected probe installation and avoidance of unnecessary work, including in-situ balancing.

Planning lesson: define the diagnostic task you expect to improve, who reviews the findings, and how site acceptance will be demonstrated.

This is a manufacturer-reported customer story, not an EWOLO CONTROL project. It does not establish an outcome for another installation or replace release-specific migration instructions.

Make the hardware enquiry specific

A software project can also uncover a hardware requirement: a revision differs from the drawing, a standby rack needs a spare, or the shutdown includes a component replacement. List each item separately so its responsibility and cost remain clear. Send a clear nameplate photo and the complete identifier. A series name such as “3500” is useful context, but it is not a complete ordering requirement.

Information to sendFull part number, suffix and revision
Why it helpsKeeps the enquiry tied to the requested variant
Information to sendNameplate and connector photos
Why it helpsHelps resolve an unreadable or incomplete identifier
Information to sendInstalled rack and application
Why it helpsGives engineering the context needed for review
Information to sendQuantity and required-on-site date
Why it helpsDefines the purchasing requirement and timing
Information to sendDelivery country and required documents
Why it helpsAllows shipping and document requirements to be discussed

If a replacement or alternative is proposed, ask for the matching evidence and the conditions that apply. Obtain site engineering approval before ordering against that proposal.

Questions before the upgrade and purchase

If System 1 stops showing fresh data, does that prove our 3500 protection has failed?

That symptom alone does not establish the protection status. Investigate the missing current data and have the responsible engineer assess the rack indications and protection functions using approved site procedures. Do not treat an unchanged software screen as proof that protection is either normal or failed.

Can we leave historical-data checks until after production resumes?

Agree which historical records must remain available before work starts. Include representative history, new acquisition and relevant alarms in the acceptance checklist. Keep any unresolved history requirement open for the responsible engineer’s decision. Opening the application successfully does not demonstrate that engineers can retrieve the information needed for comparison or investigation.

Can I start an enquiry if the label is incomplete?

Yes. Send the clearest available photos and explain which characters or revision details are missing. Keep the identification open until those details are confirmed; do not approve an order based only on a similar-looking item.

What should I ask for to confirm new, unused condition?

Ask for item-specific product, label and packaging photos, and written condition confirmation. Packaging appearance alone does not establish operating condition or test coverage.

Does an inspection photo prove that the unit was functionally tested?

No. Ask what was checked and request the relevant record where testing is claimed. Visual inspection, power-on checks, functional tests and system tests describe different scopes.

How should I handle a tight shutdown date?

State the required-on-site date and destination at the start. Ask the quotation to distinguish item availability, dispatch timing and transport assumptions. Agree the delivery basis before placing the order.

Prepare your Bently Nevada parts enquiry

Our supply policy is new, unused parts only. Item availability, delivery timing, documents and applicable warranty terms must be confirmed in the written quotation.

Provide:

  • Full part number / suffix / revision
  • Quantity
  • Nameplate or parts list
  • Delivery country
  • Required-on-site date
Submit your parts list
Email confirmation → Requirement review → Written quotation

Scope note: This enquiry is for hardware sourcing. Confirm System 1 software licensing and migration scope with your relevant software provider.

About the author

Eleanor

Sales & General Manager · EWOLO CONTROL

Eleanor focuses on industrial automation spare-parts sourcing and procurement support. She helps maintenance teams, procurement professionals and system integrators clarify complete part numbers, revisions, product condition and delivery requirements before quotation. Her articles turn these purchasing questions into practical checklists for installed systems.

Manufacturer references

[1] Bently Nevada, System 1 v25.2 What's New, document 125M6426, November 2025. Page 4: database transition, backup and subscription notes. Page 7: release support matrix.

Read the manufacturer release notes (PDF)

[2] Bently Nevada, Decision Support Analytics Achieve Value Realization on Day 1. Manufacturer customer story describing a mid-2020 System 1 20.1 project.

Read the manufacturer customer story

References reviewed 19 October 2026. The release notes and historical customer story have different scopes; confirm applicability to the actual installation.

leave a message

No online payment is requested. Final price and terms are supplied in a written quotation.